Only $468 million of Applied Digital’s (NASDAQ: APLD) freshly minted $41 billion in contracted revenue is actually scheduled to arrive before the end of its fiscal year in May 2027.
That gap between headline promise and near-term cash is the central tension facing the data center developer after it announced a new 150-megawatt, 18-year lease with a “tier-one investment-grade hyperscaler” on Monday.
The announcement triggered a surge of as much as 31% in APLD shares before the stock settled at $13.82, a gain of just over 20% by the close of trading.
The timing was notable: Monday’s rally followed Friday’s close of $11.49, which had marked the lowest point in the past year for the company’s stock.
Despite the single-session bounce, shares remain 72% below their 52-week high of $49.65 set on May 28, and the stock is still down 44% on the year.
The latest quarterly filing, submitted October 7 before the new deal was announced, showed $35.7 billion in minimum contracted lease payments outstanding, with the vast majority deferred well into the future.
Payments climb to $1.58 billion in the fiscal year following May 2027 and $2.36 billion the year after that, while $26.6 billion of the total is not due until after May 2031.
The deferred structure reflects construction reality: Applied Digital currently operates 250 megawatts of AI data center capacity at its Polaris Forge 1 campus in Ellendale, North Dakota, against 1,410 megawatts under contract.
The remaining capacity is scheduled to come online between late 2026 and 2028, including a 210-megawatt facility leased in June to a separate investment-grade hyperscaler that is not expected to be delivered until the first half of 2028.
Construction delays carry a contractual sting, as the company’s own annual report discloses: “Under certain circumstances, lessees may have the right to terminate applicable leases if there are significant delays in construction.”
The same filing acknowledges that Applied Digital “may not be able to release the applicable data center in a timely or profitable manner” if a lease is terminated.
The company’s 7% notes due 2031, issued through a subsidiary, contain a provision requiring that certain tenant termination fees be used to retire that debt unless a replacement tenant is secured.
Financing the construction pipeline has already stretched the balance sheet considerably, with long-term debt climbing to $6.26 billion as of August 31 from $4.96 billion just three months prior.
Quarterly interest expense jumped to $77.4 million from $8 million in the same period a year earlier, even as revenue expanded sharply to $341.9 million from $80.9 million year-over-year.
The company reported an operating loss of $62.4 million for the quarter and held $2.95 billion in cash, leaving limited tolerance for project slippage.
Adding a macro dimension to execution risk, LPL Financial Chief Equity Strategist Jeffrey Buchbinder noted in a Monday commentary that the six largest U.S. hyperscalers are expected to produce negative free cash flow in both 2026 and 2027, citing Bloomberg estimates.
Buchbinder also warned that political headwinds will likely slow data center construction, “though probably not until 2028,” and that rising financing costs could threaten project feasibility precisely when several of Applied Digital’s facilities are scheduled for delivery.
The new 18-year lease term does exceed the roughly 15-year term on the June agreement, signaling longer commitment from tenants, but the ultimate value of the $41 billion portfolio depends entirely on whether buildings open on time.
Investors watching the AI infrastructure buildout will likely treat the company’s next quarterly report as a key checkpoint for whether its 2027 construction schedule is holding.
Until the bulk of that contracted capacity is operational and generating rent, the $41 billion figure represents potential income rather than assured revenue.