A construction workforce exceeding 2,000 skilled tradespeople is now assembling what stands as the largest natural gas-powered energy facility currently under construction anywhere in the United States.

The project, Homer City Generation’s redevelopment of the former Homer City Generating Station in Indiana County, Pennsylvania, reached a pivotal equipment milestone in late September 2026.

Two of seven GE Vernova (NYSE: GEV) 7HA.02 high-efficiency natural gas turbines were delivered and set at the Homer City Energy Campus, marking the start of major equipment installation at the site.

When fully operational, the campus is projected to produce up to 4.4 gigawatts of power, a figure that underscores the sheer ambition of the undertaking relative to anything else currently being built in American gas generation.

Five additional turbines remain to be delivered, with rail transport scheduled to continue later this year and throughout 2027, keeping the project on pace for a first-power target in early 2028.

Alongside the turbine arrivals, crews have completed installation of the first half of the site’s heat recovery steam generators, with the remaining HRSG units expected to arrive into next year.

Heavy-haul specialist Edwards Moving and Rigging managed the physical transport of equipment, moving 20 pieces from Schenley, Pennsylvania to the campus since September 2026, coordinating closely with the Pennsylvania Department of Transportation, local police and traffic control personnel.

Willie Sanford, Large Project Manager for Edwards Moving and Rigging, noted the logistical complexity involved, saying: “Moving oversized equipment is no small undertaking, and the cooperation and support from surrounding communities have played an important role in helping us complete these moves safely and successfully.”

The project has maintained a zero OSHA-recordable incidents record across its entire construction history to date, a safety benchmark that Homer City Generation, partner Kiewit, and GE Vernova have each cited as central to their operational standards on site.

Dave Ross, CEO of GE Vernova’s Gas Power business in the Americas, framed the delivery within a broader demand narrative, stating: “As electricity demand continues to grow, projects like Homer City can help deliver reliable, efficient power at scale.”

Homer City Generation CEO Corey Hessen described the turbine arrivals as consequential not just technically but economically for the surrounding Indiana County region, pointing to what he called “an unprecedented level of economic opportunity” being brought to the community.

Edwards Moving and Rigging is expected to return to the area in 2027 as the next phase of equipment transport operations begins, with the remaining turbine deliveries continuing to move through the pipeline toward the campus’s 2028 commercial power target.